- Home
- About Campus Facilities
- Contact Us
- Organization Chart/Directory
- Departments
- Energy Management
- Facility Operations
- Landscape Services
- Planning, Design & Construction
- Space Planning & Management
- Employment Opportunities
- Training
- Safety Program
- Information & Services
- Outages and Closings
- Service Requests
- Work Order Information
- Vehicle Rentals
- Sign Shop
- Movers
- Building Coordinator Information
- Contractor & Consultant Information
- Projects Map
- Links
- MU Campus Master Plan
- Mizzou Botanic Garden
- Facilities Focus Archives
Planning, Design & Construction
Upcoming Projects
Following is a list of future construction projects. We have provided information on the current scope of the project as well as the current cost estimate and anticipated ad & bid dates.
| Project Number |
Project Title | Project Scope | Est. Ad Date |
Base Estimate & Alternates |
Est. Bid Date |
| CP062102 | Power Plant - Replace Cooling Towers | Replace the existing cooling towers on the roof of the power plant with new towers located at the same level on the west side of the gas turbine building. | 04/21/2008 | $13,500,000 | 05/20/2008 |
| CP080861 | General Site – Virginia Avenue Extension | This project will design and install new and reconstructed roadway infrastructure with storm sewer utilities servicing the SE Gateway locations. | 07/29/2008 | $1,700,000 |
08/19/2008 |
| 400603 | Brady Commons - Student Center/Brady Commons Renovation | Develop program and plans to expand and renovate the Brady Student Center. | 11/03/2008 | $28,125,334 | 12/09/2008 |
| CP071041 | Various Locations - Renovate Hudson, Gillett & Rollins Halls | Develop renovation plans for Hudson and Gillett, two seven story residence halls, with current capacity of 497 students to revised capacity of 420 beds each. In addition to interior modifications required to make this housing more attractive to students and support programmatic living and learning initiatives, this project will include the addition of central air conditioning, elevator improvements, replacement windows, masonry repairs as needed and other interior upgrades to both residence halls and the lower level of the adjoining Rollins Hall. Previous Critical Measure efforts, completed in 2002 included electrical upgrades and fire alarm upgrades in the towers and some limited efforts in Rollins. Previous Critical Measure efforts, completed in 2002 included electrical upgrades and fire alarm upgrades in the towers shall be incorporated into the renovations. | 10/13/2008 | $38,995,000 | 11/20/2008 |
Disclosure: This data is intended for information purposes only. This is not a complete list, nor is the information provided guaranteed to be correct. Stated dates are subject to change. This page is updated monthly.
![]()