Campus Facilities

Planning, Design & Construction

Substantial Completions

CP090442 – Hospital Garage-Structure Repairs
We have accepted for substantial completion the entire project as of 7:00 pm, Saturday, October 17, 2009.

CP081641 – Replace Manhole & Create New Duct Bank from Virginia Ave to Hospital Dr.
We have accepted for substantial completion the entire project as of 5:00 pm, Thursday, August 13, 2009.

CP090631 – Schweitzer Hall-Lab Fit-out for Room 240
We have accepted for substantial completion the entire project as of 10:00 am, Thursday, October 1, 2009.

100843 – Life Sciences Business Incubator Steps
We have accepted for substantial completion the entire project as of 8:00 am, Wednesday, September 16, 2009.

CP081631 – MURR Shipping and Receiving Building
We have accepted for substantial completion the entire project as of 3:00 pm, Tuesday, September 15, 2009.

CP080811 – Medical Science Addition-Renovate MA406 into Classroom
We have accepted for substantial completion the entire project as of 4:00 pm, Thursday, September 3, 2009.

CP100521 – General Site-Chipseal Providence Point Drive
We have accepted for substantial completion the entire project as of 3:30 pm, Thursday, September 3, 2009.

CP090991 – University Hospital-Reroof Eye Research Building
We have accepted for substantial completion the entire project as of 3:00 pm, Wednesday, September 3, 2009.

CP062533 – SE Gateway Utilities Construction-Phase 3A
We have accepted for substantial completion the entire project as of 12:00 pm, Thursday, September 3, 2009.

CP060241 – Mid-Campus Defoe Graham Housing
We have accepted for substantial completion the site and building exteriors as of 4:30 pm, Monday, September 1, 2009.

CP091781 – Vet Med West Second Floor Restroom Renovation
We have accepted for substantial completion the entire project as of 4:00 pm, Monday, August 31, 2009.

CP081881 – Sinclair School of Nursing-Renovate Auditorium S255
We have accepted for substantial completion the entire project as of 4:00 pm, Tuesday, August 25, 2009.

CP091771 – Lewis Hall Misc. Renovations
We have accepted the entire project for substantial completion as of 4:00 pm, Wednesday, August 19, 2009.

CP091781 – Vet Med West Second Floor Restroom Renovations
We have accepted for partial occupancy rooms W222 and W237 as of 4:00 pm, Wednesday, August 19, 2009.

CP070449 – Orthopedic Institute-Site and Underslab Electric
We have accepted for substantial completion the entire area as of 4:00 pm, Friday, July 31, 2009.

CP051262 – Lafferre Hall Reconstruct 1922 Addition
We have accepted by substantial completion the entire project as of 4:30 pm, Monday, August 17, 2009.

CP100201 – Various Locations-Asphalt Repairs
We have accepted for substantial completion the entire project as of 12:00 pm, Friday, August 14, 2009.

CP100071 – Green Tennis Court
We have accepted for substantial completion the entire project as of 7:00 am, Friday, August 14, 2009.

CP092401 – General Site-Replace Culvert under Champions Drive
We have accepted for substantial completion the entire project as of 2:00 pm, Thursday, August 13, 2009.

CP100061 – Various Locations-Parking Lot Repairs
We have accepted for substantial completion the entire project as of 2:00 pm, Thursday, August 13, 2009.

CP090792 – Replace Elec Duct Bank at Monk and Hospital Dr.
We have accepted for substantial completion the entire project as of 4:30 pm, Friday, July 24, 2009.

CP100061 – Various Locations Parking Lot Repairs
We have accepted for partial occupancy parking lot WC–14 as of 8:30 am, Wednesday, August 5, 2009.

CP092141 – Mid MO MHC – Site Signage
We have accepted for substantial completion the entire project as of 10:00 am, Tuesday, August 4, 2009.

CP062532 – Southeast Gateway Utilities Construction-Phase 3A
We have accepted for substantial completion the entire project as of 12:00 pm, Thursday, July 30, 2009.

CP060241 – Mid – Campus Housing Defoe/Graham
We have accepted for substantial completion the Defoe/Graham connector complex all floors (interior only) as of 4:30 pm, Monday, July 20, 2009.

CP051262 – Lafferre Hall – Reconstruct 1922 Addition
We have accepted for partial occupancy all project work except for main entry space and stairwell, elevator, and all work related to ASI’s #28, 29 and 39 as of 4:00 pm, Monday, July 20, 2009.

CP071561 – Keene Medical Building-OB/GYN Continence Clinic
We have accepted for substantial completion the entire project as of 4:00 pm, Thursday, July 16, 2009.

CP080861 – General Site – Virginia Avenue Extension
We have accepted for substantial completion the entire project as of 5:00 pm, Tuesday, June 30, 2009.

CP082191 – General Site – Stankowski Field Truf Replacement
We have accepted for substantial completion the entire project as on 4:30 pm, Thursday, July 9, 2009.

CP060241 – Mid Campus/Defoe Graham Housing
We have taken substantial completion on the south building (interior only) as of 2:30 pm, Thursday, June 25, 2009.

CP092131 – Fulton Clinic-Replace Roof
We have accepted for substantial completion the entire project as of 1:00 pm, Wednesday, June 24, 2009.

CP080681 – South Farm – Discovery Ridge Various Improvements
We have accepted for substantial completion the entire project as of 4:00 pm, Monday, June 15, 2009.

CP091591 – CRH Fireproof
We have accepted for substantial completion the entire project as of 10:00 am, Wednesday, June 03, 2009.

CP091991 – Strickland Hall
We have accepted for substantial completion the entire project as of 10:00 am, Tuesday, May 26, 2009.

CP081851 – Chiller Replacement
We have accepted for substantial completion the entire project as of 4:00 pm, Friday, May 22, 2009.

CP052142 – Manhole Repairs
We have accepted for substantial completion the entire project as of 4:00 pm, Friday, May 22, 2009.

CP090221University Hospital/MRI Relocation
We have accepted for substantial completion the entire project as of 4:00 pm, Monday, May 11, 2009.

CP060241 – Mid Campus Defoe/Graham Housing
We have accepted for substantial completion the West Building’s Interior only as of 4:30 pm, Thursday, April 30, 2009.

CP090221 – University Hospital/MRI Location
We have accepted for partial occupancy rooms 25 – 19 MRI exam room, 25-17A equipment room, 25-17B storage room, 25-18 passage corridor, 25-17 passage corridor and the east work area of control room 25-20 as of 8:00 am, Monday, March 30, 2009.

CP082262 – KOMU TV-News Set Design & Installation
We have accepted for partial occupancy the epoxy floor in studio 8A as of 11:00 am, Friday, March 20, 2009.

CP081921 – Ellis Fischel-Reroof
We have accepted for substantial completion the entire project as of 2:00 pm, Wednesday, February 25, 2009.

CP081031 – MRC-Replace and Add Equipment & Alarms
We have accepted for substantial completion the entire project as of 1:00 pm, Tuesday, January 6, 2009.

CP060241 – Mid – Campus Defoe/Graham Housing
We have accepted for partial occupancy the south portion (shell space) of the West Building’s basement as of 8:00 am, Monday, February 2, 2009.

400601 – Student Center/Brady Commons Expansion
We have accepted for substantial completion the entire project as of 3:30 pm, Thursday, January 29, 2009.

CP090301 – Virginia Ave Housing – Replace Water Line
We have accepted for substantial completion the entire project as of 4:00 pm, Wednesday, January 7, 2009.

CP062122 – New Utilitiy Tunnel from Power Plant to Maryland Ave
We have accepted for partial occupancy phase 1, excluding mechanical piping and electrical items, at 4:00 pm, Sunday, January 4, 2009.

 

 

 

 

This file dynamically generated: November 7 2009
xhtml css