MU bike trail makes the town-and-gown connection
verything was in place. Campus Facilities’ Construction
Management unit was ready for the contractor to hoist a bridge
over Hinkson Creek and bring MU’s three-year-old Bike Trail
Project that much closer to completion this fall.
But then the matter of the minnows surfaced. A habitat survey
by the Missouri Department of Conservation brought up the issue
of the breeding season of a particular minnow in the creek, which
threatened once more to throw the completion of the trail into
2002.
“The crane needed to set the bridge would actually set up
in the creek, causing a disturbance in the creek bed,” said
Bob Berg, construction project manager. “The hold directive
given to the contractor by the Department of Natural Resources
would allow the minnow to spawn but delayed progress until late
last month.”
Accomodating the bats
 |
| Ron Libbert, of Schneider Excavating, prepares the east approach
to the Hinkson Creek bridge abutment. |
Prior to the minnows were delays caused by the nesting habits
of migratory Indiana gray bats.
“The bat nests in the loose bark of trees in the area,” said
Berg. “We, of course, accommodated these creatures and then
had only a small window of time last fall during which Landscape
Services could remove the trees before the bats returned in April
and May.”
Heavy spring rains caused further delay, keeping the creek’s
silt level high — prolonging the fish-breeding period — and
saturating trail areas cleared earlier. Equipment sat idle as crews
waited for the creek to clear and the ground to dry.
Construction, however, is back on track. The fish breeding season
is over, bats are nesting elsewhere and the ground is workable.
Final construction on this Phase Two of the Bike Trail will see
a 190-foot clear-spanned truss bridge, measuring 18 feet tall at
its midsection and 10 feet tall at its ends, spanning Hinkson Creek,
and the remaining mile of the trail surfaced from Epple Field west
to where it joins the city’s M K T Trail. Truckloads of filler
dirt will be brought in to form a grade from the creek bottoms
to the surface of the M K T Trail.
The Hearnes Center Trail Head
Phase One, completed last year, starts at the bus shelter in the
Hearnes Center visitors’ parking lot and runs southwest downhill
to under Providence Road and then past the Research Park area on
Old Route K to Epple Field. Most of the trail is asphalt with a
yellow center line dividing it for two-lane traffic.
“Even though the first part of the trail drops from the
Hearnes Center to Providence Road, the trail does not exceed a
five percent grade,” said Larry Edwards, director of CF’s
Facilities Management, “and meets A D A standards for wheelchair
accessibility.”
Phase Three runs more than a mile from Providence Road east through
the Hinkson Recreation area and connects to the city’s Grindstone-Capen
Trail now under construction.
“Construction here will be quicker because there aren’t
any bridges, and should be completed by the end of the summer,” said
Berg.
Phase Four, beginning at the Student Recreation Center, is routed
over existing streets through the Stadium Road tunnel and Faurot
Field parking lot, and along Mick Deaver Drive to the Hearnes Center
parking lot. Construction Services will widen sidewalks where necessary,
and an asphalt lane is being built along the west side of the drive
as part of Planning, Design and Construction’s 2001 summer
paving project.
More than a bike trail: the green belt system
MU’s bike trail is part and parcel of the City of Columbia’s
long-range plan for bike and walking trails within a green-belt
system encircling the city. The Bear Creek green belt north of
town will connect to the Perche Creek section west of Columbia
and to the Hinkson Creek green belt running north and south east
of town. MU’s bike trail not only completes the circuit across
south Columbia, but also connects the system to the M K T Trail.
The work years ago of a now-defunct faculty, staff and student
subcommittee of the Campus Planning Committee resulted in the design
of the trail route and the securing of funds from the Missouri
Department of Transportation to cover 60 percent of its cost. MU’s
Parking and Transportation provided the remaining funds.
“The trail we have now is more than a bike trail,” said
Edwards. “It’s a multi-use trail, meandering through
beautiful sections of the campus and south Columbia. It’s
suitable for biking, walking, jogging, and wheelchair use. Commuters
will ultimately be able to bike to campus. Anytime a bike is used
means that one more parking space is freed up, which helps with
traffic and parking on campus.”
|