Press Box project finished for season opener
hat seemed like an insurmountable task turned into a challenge
that MU’s Planning, Design and Construction tackled head
on and conquered. The Memorial Stadium Press Box Project was begun
in November at the end of the 1999 football season and completed
in time for MU’s Sept. 2, 2000, opening win against Western
Illinois — a mere nine months later.
“The project succeeded because failure was not an option
for us,” said
Don Guckert, Planning, Design & Construction’s director. “More
than anything, the workforce felt a loyalty and commitment to MU
and MU Athletics.”
Thanks to the cooperation of MU Athletics,
PD&C, architect
Ellerbe Beckett, and contractor Walsh Construction, MU boasts one
of the finest luxury suites and press boxes in the Big 12.
MU planned
ahead to make the project run as smoothly as possible. Before construction
began, Ellerbe-Beckett architects, MU and UM
officials involved in the project toured renovated stadiums at
Notre Dame and the University of Toledo; a similar team met with
Walsh Construction owners in Chicago and visited the University
of Kansas and Kansas State to learn from their press-box-and-suite
projects, which were completed in September 1999.
Jim Henley, PD&C’s
construction engineer on the project, also visited steel, precast
and brick suppliers’ plants to
secure personal and first-hand commitments to meeting critical
delivery dates, and was in constant contact with several other
vendors whose deliveries were critical.
Walsh, one of the 50 largest
construction companies in the United States, was new to the mid-Missouri
market and relied heavily on
Construction Management’s contacts to secure local labor
union workers, subcontractors and suppliers.
"On more than one occasion,
the Walsh people said they had never worked with a more proactive
owner than MU,” Guckert said. “We
really appreciate the compliment and realize that everyone’s
efforts helped in the success of the project. Mike Alden, for example,
often took time to recognize the workforce, which helped motivate
them to meet the deadline.”
In all, the press box and suites
project, about 82 percent of the size of Reynolds Alumni Center,
was completed in 291 days (See "Press
Box & Suites Timeline).
Reynolds, however, took 615 days to complete. Moreover, unlike
the Reynolds
Center, the press box project was built on “stilts” 80
feet in the air, which required that workers and materials be hoisted
into place.
The contractor had to build at a rate of more than $1
million per month (or $50,000 per day), based on a five-day work
week, to complete
the project in time for the season opener.
|