Press Box & Suites Timeline
1993
Athletics Department includes Press Box and Suites Project in
its Master Plan.
1998
Oct. 1: Planning, Design & Construction’s Project Management
receives a Project Request Form from the Athletics Department.
Nov. 23: Ellerbe-Beckett Architects chosen.
December: Ellerbe-Beckett
hired on a limited agreement to begin drawings prior to Board
of Curators approval.
1999
Jan. 28: Curators officially hire Ellerbe Beckett
February: UM and MU officials and Ellerbe-Beckett Architects visit
Notre Dame and the University of Toledo to see both large and small-scale
press-box-and-suites projects.
March 28: PD&C receives schematic
design, rendering, plans and cost from Ellerbe-Beckett.
May: Curtiss-Manes-Schulte,
Eldon, Mo., chosen as contractor for drilled pier work and uitility
relocation
June-August: Foundation poured for press box, and utilities relocated.
Area restored before first game of the ’99 football season.
Aug. 4: Walsh Construction, Kansas City, Mo., chosen as contractor
for Press Box & Suites project.
Aug. 17: Walsh hired on a limited
agreement to begin detail drawings for structural steel, rebar
and structural precast prior to Board
of Curators approval.
Sept. 3: Curators officially hire Walsh
Construction.
Nov. 13: Tigers last home game of ’99 season.
Nov. 14: Construction
Engineer Jim Henley gives Athletics Department one day to “remove
every salvagable product from the old press box and lounge.”
Nov.
15: Foundation work and demolition of the old press box and lounge
begins.
December: North and south stair-towers erected.
Crews works in two shifts from 7 a.m.-11 p.m., six days a week
and, later, seven days a week.
2000
January: Structural precast support/facade started up through
and including the Club Level, or third floor, and running between
the north and south stair-towers.
February: Superstructure erected up through and including the Photo
Deck or the sixth floor. Crews cannot work safely at night so begin
10-hour days, six days a week, sometimes 12-hour days seven days
a week, to make up time lost on foundation work. Height and radius
design of structure, and operating a crane in an in-use parking
lot proves difficult at times.
Late March: Superstructure completed and steel
(or first of three layers) roof installed.
April: Interior work
in full swing. Contractor plans new “critical
path method” schedule to complete work before opening game,
Sept. 2. Trades are stacked, meaning 150 people of all trades work
side-by-side instead of allowing one to finish before another begins.
Additional workers hired. Everyone works 10-hour days, six days a
week for duration of project. Tepco window installation begins.
The operable windows open on an automatic-garage-door mechanism.
Two windows each day are installed.
May: Wooden (or second layer) roof installed. Tepco Window installation
continues.
June: Nearly half of the contracted work, or $5 million, was completed
in the last 90 days of the project. Sheet-metal (or third layer)
roof installed. Tepco Window installation complete. MU tradespeople
brought in to install telephone, scoreboard controls, public address
system, interior press box sound and television systems, among
other services provided by MU.
July-August: Painting, tiling, carpets, ceiling grids and furnishings
installed.
Aug. 7: Club Level (third floor) complete
Aug. 14: Suite Level
(fourth floor) complete.
Aug. 19: 3,000 people attend open house to tour Club and Suite
levels.
Sept. 1: Press Box and Photo Deck (fifth and sixth floors) and
all exterior work complete.
Sept. 2: Tigers season begins with home win against Western Illinois.
|