Construction 1998: A boom year comes to an end
by Jon Stemmle
tudents for years have been saying that Missouri's
school color should be orange because of all the pumpkin-colored
fencing around the campus. Those cries turned louder in 1998 as
MU was swept away in a construction tidal wave.
This wave, however, will help bring MU into the
next millennium. Projects in 1998 totaled nearly $90 million, including
more than $67 million that went toward nine projects.
"It's been a busy and extremely challenging year for construction
management, the same as it was for project management at the front
end of this work," said Don Guckert, director of Planning, Design & Construction.
"It's
dramatic how far we've come in a short time and how much we have
to show for it."
Catch a wave
The $140 million worth of projects worked on in F Y97
happened as a matter of chance. Many of the projects, such as the
utility improvements on the Francis Quadrangle and White Campus,
were years in the making, while others were relatively new. Each,
however, was driven by finances to begin roughly at the same time.
With the funds available to replace 20-year-old pipes and upgrade
buildings into the next century, PD&C wasted no time.
"Spikes in the construction totals graphs are fickle,'' Guckert
said. "I
like to look at this as a five-year snapshot. If you assume
we are in the middle of a five-year window, it would total approximately
$350 million or about $60 to $70 million per year. The bottom line
is that's pretty healthy and active."
To put these dollar amounts in perspective, the
original funding designated in 1839 for the establishment of the
university was $100,000; its first building, Academic Hall, built
in 1843 cost $75,000.
One-hundred-fifty-five years later, MU is in the
process of constructing a Critical Care Addition, which alone costs
$46 million.
Building a Better Mizzou
Each renovation and construction project, and two
utility improvements, were unique in size, scope and difficulty.
The first project completed, in April 1998, was the
Chemistry Building Addition. This long-overdue structure was the
first major upgrade since the 1930s of MU's chemistry facilities.
As the Chemistry Building Addition neared completion,
the White Campus and Francis Quadrangle Utility projects were beginning.
Both highly-invasive projects ripped up landmark areas of the campus.
Although, over the summer, they were daily hassles for students
and faculty, both projects help to create a new utility infrastructure,
setting the stage in the coming years for air-conditioning and
other conveniences.
In May, the Audrey J. Walton Track-Soccer Field-Stadium
was completed. A deadline to have the project completed so that
MU could host the Big 12 Outdoor Track and Field Championships,
along with poor weather conditions caused by the El Niņo phenomenon,
imposed difficulties on the project.
June through August, then, was the most active period
of the year — seven projects were completed: Connaway Hall
Renovation, Telecommunications Addition, Anheuser-Busch Natural
Resources Building, and the Black Culture Resource Center were
opened in June; Dan Devine Pavilion/Dutton Brookfield Addition
and Hitt Street Parking Garage were opened in July; and the Jesse
Hall Exterior Repair & Restoration were opened in August. "This
was one of the most challenging times for us. Not only were we
extremely busy completing these buildings, but we were dealing
with the disruptive utility projects on campus,'' said Guckert. "Campus
Facilities did a great job with communication and preparing the
campus for what was coming. No one was surprised when the corridor
was torn up. It was handled very well."
While most talk centered on the high-profile Jesse
Hall and Francis Quadrangle utility projects, it was the Dan Devine
Pavilion and the Anheuser-Busch Natural Resources Building that
provided more problems for PD&C.
"Schedule-wise the Dan Devine Pavilion was the most
challenging as we had to have it done for coach (Larry) Smith in
time for the football season," Guckert said. "Anheuser-Busch was
challenging in terms of design because it was such a large, intricate
structure."
The next wave
Although 1999 may not be the monster year of building
that 1998 was, construction costs will still be well above $30
million.
The top project in 1999 to be completed is the $46
million Critical Care Addition. This project, which began Nov.
1996, is the most expensive structure to date.
Other projects that will wrap up in 1999 are the
Bicycle Trail ($600,000); resurfacing of the Hearnes Center indoor
track ($500,000); Schlundt/Chemistry Renovation ($8.9 million);
Eckles Hall Addition ($7 million) and White
Campus Greenhouse.
"We may not see the numbers we saw in 1998 again
for awhile, but we will still be busy,'' Guckert said.
Photos
of 1998 construction projects
|