Construction List: July/August 1998
- Memorial Union
Partial renovation of the first floor south wing
Cost: $322,724
Completion: November 1998
- Engineering Building East
Tuckpointing & roof replacement
Cost: $736,000
Completion: Septmeber 1998
- Schlundt/Chemistry Renovation
Cost: $8,900,000
Completion: August 1999
- Critical Care Addition
Cost: $46,000,000
Completion: June 1999
- Eckles Hall Addition
Cost: $7,000,000
Completion: October 1999
- Hearnes Center
Roof Replacement
Cost: $1,000,000
Completion: October 1998
- Francis Quadrangle
Below grade improvements
Cost: $1,900,000
Completion: January 1999
- White Campus
Utility Improvements
Cost: $1,800,000
Completion: December 1998
- Old Alumni Center
Renovation office space
Cost: $753,545
Completion: September 1998
- McHaney Hall
Second floor renovation
Cost: $709,373
Completion: January 1999
Note: This is a representative — not a complete — list
of construction projects under way on the MU campus.
|
Facilities Focus is a newsletter published
by department to share news about MU facilities with the campus community. If you have questions or
comments about this web site, please send them to Campus Facilities Communications, email:
;
mail address: 180 General Services Building, Columbia, MO 65211;
telephone: 573-882-3327; fax: 573-882-5603.
Revised 7/2005 |
|
|