Construction List: Fall 1996/Winter 1997
- Ambulatory Care
Cost: $12,600,000
Completion: February 1997
- Medical Science-Renovate 6th Floor
Cost: $5,600,000
Completion: July 1997
- Memorial Stadium Improvements
Cost: $10,700,000
Completion: August 1997
- Brady Commons Bookstore Addition
Cost: $3,200,000
Completion: September 1997
- Vet Medicine East Renovation
Cost: $7,200,000
Completion: November 1997
- Chemistry Addition
Cost: $8,700,000
Completion: May 1998
- Hitt Street Parking Structure
Cost: $12,000,000
Completion: July 1998
- Anheuser-Busch Natural Resources Building
Cost: $18,500,000
Completion: August 1998
Note: This is a representative list — not a complete list — of
construction projects occurring on the MU campus.
|
Facilities Focus is a newsletter published
by department to share news about MU facilities with the campus community. If you have questions or
comments about this web site, please send them to Campus Facilities Communications, email:
;
mail address: 180 General Services Building, Columbia, MO 65211;
telephone: 573-882-3327; fax: 573-882-5603.
Revised 7/2005 |
|
|