Construction List: Fall 1996/Winter 1997

  • Ambulatory Care
    Cost: $12,600,000
    Completion: February 1997

  • Medical Science-Renovate 6th Floor
    Cost: $5,600,000
    Completion: July 1997

  • Memorial Stadium Improvements
    Cost: $10,700,000
    Completion: August 1997

  • Brady Commons Bookstore Addition
    Cost: $3,200,000
    Completion: September 1997

  • Vet Medicine East Renovation
    Cost: $7,200,000
    Completion: November 1997

  • Chemistry Addition
    Cost: $8,700,000
    Completion: May 1998

  • Hitt Street Parking Structure
    Cost: $12,000,000
    Completion: July 1998

  • Anheuser-Busch Natural Resources Building
    Cost: $18,500,000
    Completion: August 1998

Note: This is a representative list — not a complete list — of construction projects occurring on the MU campus.


Skip to other articles in this issue
Facilities Focus is a newsletter published by Campus Facilities' Communications department to share news about MU facilities with the campus community. If you have questions or comments about this web site, please send them to Campus Facilities Communications, email: cfweb@missouri.edu; mail address: 180 General Services Building, Columbia, MO 65211; telephone: 573-882-3327; fax: 573-882-5603.

Revised 7/2005

Facilities Focus Online home | Facilities Focus Archives home | Read the current issue | Campus Facilities home | University of Missouri-Columbia home